SuDS banner
CIRIA logo

 

 

 

Follow sudsulike on Twitter

 

 

SuDS-related links


Keeping ahead
with SuDS

Attend SuDS training to keep ahead of the competition and to deliver innovative solutions in line with recognised good practice.

click here


 

home > using SuDS > case studies > Bushloe High School

Bushloe High School, Leicestershire

Location

B582 Station Road, Wigston, Leicestershire

map - Bushloe school

Fig 1: Location of Bushloe high school

Description

The project is a new high school catering for Years 6-9, serving the Wigston area of Leicester.  It lies adjacent to The Abington School (another high school) and Guthlaxton College. The building is served by a large, 80-space car parking area for staff.  The site lies at roughly 103mAOD, with playing fields to the south. The context is suburban.  The whole site area drained is around 2.6ha.  Surface water drainage is to the north to a combined sewer along Station Road.  Building was completed in late 2005.

The SuDS scheme at Bushloe provided us with far more than a drainage system, it has enabled a whole educational landscape to develop. The swales, as well as looking good, have become useful habitats to study in science and geography. The pond to which all the water drains has developed into a haven for all sorts of wildlife from water boatmen and dragonflies to ducks. We now have a dipping platform installed there so that classes can study this now naturalised habitat that is so close to our school.” Mark Batchelor – Head of Geography

 

Site map

Fig 2: The quotations from the Head of Geography, Mark Batchelor, perhaps show how highly the school regard their SuDS and the landscape it sits in.  The detention basin is especially engaging and students and staff use it routinely.  Originally, the basin wasn’t fenced but, against the protests of staff, fencing has recently been installed, making access harder.  The school have installed dipping platforms to improve curriculum use still further.

 

 

Main SuDS used

The SuDS employs the concept of a ‘treatment train’.  The car parking and external works were redesigned to maximise above ground SuDS and reduce costs.  A planning condition (imposed after consultation with Oadby and Wigston Council) required the landscape to be an environmental teaching resource and this is a major feature of the SuDS.  Some limited underground drainage was used, such as to connect under heavily trafficked areas and the play areas that surround the building.

Entrance

Fig 3:Summer Flag - The Eco-Schools flag being proudly flown at Bushloe. 

 

How it works

A bio-swale system (western and eastern) carries water from the car parks south hard surfaces to a detention basin control structure to the combined sewer.  Water is collected conventionally from the building roof and fed directly to the basin.

Bio-swales are very shallow and have been carefully graded side slopes to enable mowing.  This is now under the direction of school staff who keep vegetation longer to promote species diversity.  Several re-sowings and planting of marginal and aquatic species have occurred since 2005.

 

 

 

swale

attenuation

Fig 4: Mown Swale - Several years after completion, swales at Bushloe, against the wishes of staff, were still being amenity mown.  This regime has now been relaxed to enable plant communities to diversify.

Fig 5: Attenuation Basin - Initially some algal bloom was noticed which gradually reduced as the system matured.  How this has happened has been used as a teaching aid to show eutrophication principles in biogeography.

 

Specific details

Soils are predominantly clay and have been heavily re-worked.  Ponds and swales are not lined.

The scheme was designed to attenuate the 1 in 30 year return period Critical Duration Event. The hydraulic model was also tested to ensure that there would be no flooding off site for the 1 in 100 year plus climate change Critical Duration Event.

An oil separator was not required to prevent pollution. Instead water quality improvements were achieved throughout the treatment train, within swales, grassed areas and in the pond. The treatment train does not require power and is not susceptible to mechanical failure.

During 2009 the swales (fig 2) were left un-mown to see how planting developed with the bulk of the other grassed areas amenity cut.  Several grass areas, have been left longer for invertebrates and form part of the school’s ‘outdoor lab’.  

 

Benefits


Challenges

The following chanlenges were overcome during the project:

Reassurance provided by carrying out visits to previously installed SuDS schemes including Blythe Valley Park and seeing these work well.

 

Interaction with local authority and EA

Support from Leicestershire County Council, led by Chris Noakes and the Environment Agency.

 

Design and construction

Team:
Client: John Humphries Leicestershire County Council.
Landscape Architect: David Singleton, m+w, Leicester.
Engineer: Dave Leversha,  Buro Happold, Leeds. 
Architect: Nigel Dutton, Nigel King Leicestershire County Council.
Contractor:  Willmott Dixon, Nottingham.

sitemap