
home > good practice guidance > case studies > pilestredet
|
Project profileLocation: Project Duration (in relation to the described activities): Client: Key Statistics: Company ProfileGolder Associates (UK) Ltd Environmental and Engineering Consultants
|
Enabling waste minimisation and the use of non-primary materials:
By quantifying the concrete and masonry materials arising from the planned
demolition works, it was possible to integrate these into the new construction
planning as a resource. By using the Demolition Wizard Tool, it was possible
to assess financial and environmental costs/benefits of the various options
for this internal resource management. Based on the results of the work a
recycling target of 90% of wastes was set by the Client.
Better handling of materials:
The Demolition Wizard Tool provides assessment of scenarios relating to various
transportation, recycling, handling and segregation options for materials
and resources during site clearance and redevelopment works. This assessment
is based on the sustainability parameters of environmental and social impact,
as well as financial implications. Through analysis of the scenarios, a case
was made for the most appropriate means of separating the demolition materials
during the actual demolition.
Good practice in quantifying, costing and recording data on wastes
and materials:
A waste arising and resource requirements gap analysis at an early stage in
the planned redevelopment works allows for increased sustainability targets
to be set and achieved, for example on recycling rates, energy consumption,
and emissions. At Pilestredet Park, it was thus possible to recycle 90% of
the demolition wastes as well as reduce emissions and city traffic.
Good practice in demolition and deconstruction activities:
By identifying recyclable and reusable materials at an early stage in the
works, it is possible to incorporate sustainable demolition methods into the
Tender Documents. Although these may incur increased demolition costs, these
are more than compensated for through cost savings in disposal fees, transportation
and import of raw construction materials.
Using local approaches to encourage more sustainable practice:
A central location for sourcing materials during construction was provided
by establishing an on site demolition waste recycling plant. This reduced
the requirement for transportation of both waste off site and incoming construction
materials, reduced burden on the local disposal facilities and increased awareness
in benefits from on-site recycling.
Through the use of the Demolition Wizard Tool, the project management team at Pilestredet Park was able to achieve overall cost savings of approx. 10% on the demolition works (amounting to ca. £400,000) as well as recycling more than 90% of the demolition wastes for onsite applications in the ensuing construction works. The main barrier to utilizing the tool is timing! It needs to be used at a strategic stage, early in the planning.
Example Graphs from The Demolition Wizard Tool:
|
City traffic load for the selected scenarios at Pilestredet Park |
![]() |
|
Costs for the selected scenarios at Pilestredet Park |
![]() |
This site is not currently being updated.
All the information on the site was accurate at the time it was last
published.