(image) Banner

(image) CIRIA logo

home > good practice guidance > case studies > chieveley

A34 Chieveley M4 Junction 13 Improvement

Project description

Background
This is a Design and Build project for highway network improvement to provide full grade separation of the M4/A34 junction and remove the last ‘bottleneck’ on the A34 between the M3 and M40 Motorways. The contract value is approximately £38M.

Waste Minimisation Activity
The scheme has been developed as a sustainable transport solution with focus on continuing the sustainable thought process in the planning, design, construction, hand-over and maintenance aspects of this much needed national asset.

Materials Targeted
The requirement for imported virgin aggregates was reduced by 50,000t by use of in-situ stabilisation of soils, use of recycled demolition rubble and reuse of redundant carriageway.

Project Drivers for Waste Minimisation

  • Cost benefits including avoidance of Aggregates Levy, Landfill Tax & other waste disposal costs
  • Internal company policy requirement
  • EMS

Project profile

Location:
Chieveley, England

Project Duration (in relation to the described activities):
April 2003 to May 2004

Client:
Highways Agency

Key Statistics:
50,000 tonne reduction in primary material requirement.

Company Profile

Costain Ltd

Contractor

Project Partners:
Mott MacDonald (Designer)
RPS Planning Transport & Environment (Environmental Project Manager)
Gifford WSP (Clients Site Representative)

Project Approach to Waste Minimisation and Sustainable Use of Resources

Construction Phase Activities:

Enabling waste minimisation and the use of non-primary materials:

Using local approaches:
From a choice of local suppliers only one was picked as a supplier of recycled demolition rubble. Efforts were then concentrated on ensuring that this single supplier supplied a “quality” product to meet the project needs.

Company practice and management in supporting waste minimisation and improved approaches to resources use:

Better handling of materials:
A weekly environmental site inspection was carried out. This inspection included checks to ensure that the project Waste Management Plan was being followed and materials were being stored and segregated correctly.

Good practice in quantifying, costing and recording data on wastes and materials:
The site specific Construction Environmental Management Plan used included Waste as an objective with a target for 50% of material disposed off site in skips to be recycled.

Using specifications appropriate to enabling the use of recycled and secondary materials:
The Highways Agency Specification for Highway Works allows the use of recycled aggregate and asphalt.

Lessons Learned, Benefits and Barriers

sitem

This site is not currently being updated.
All the information on the site was accurate at the time it was last published.